7/22/2019 - Road Work Report for Week of July 22, 2019

Chip Seal Roads that still need to have Fog Seal process:

Work to be completed within two weeks. Schedule subject to change due to weather and contractor availability.

  • Bucks Hill Road
  • Munn Road
  • New Road
  • Old Waterbury Road
  • Purchase Fire Dept.
  • Spruce Brook Road (Stillson Road to Purchase Brook Road)
  • Spruce Brook Road (Meadowbrook to Stillson Road)
  • West Purchase Road

Roads to be Chip Sealed in August:

Work expected to be completed within two weeks. Schedule subject to change due to weather and contractor availability.

  • Ballantine Park
  • Beecher Drive
  • Berkshire Road
  • Crook Horn Road (Roxbury Road into Settlers Park)
  • Housatonic Trail
  • Mansion House Road
  • Old Poverty Road
  • Pascoe Drive
  • Short Rock Road
  • Sylvan Crest Drive
  • Westenhook Terrace

Mill and Pave projects tentatively scheduled for August:

  • Cedar Crest Drive
  • Georges Hill Road (from just South of Laurelwood Lane to just south of Cooper Hill Road)
  • Lakeside Road (Georges Hill Road to Fish Rock Road)
  • Parking lots within the town complex (Town Hall lower lot, Fire Dept. upper lot, Police lot)

Cold in Place recycling with surface treatment tentatively scheduled to begin July 24:

  • Brown Brook Road
  • Patriot Road

Road Reconstruction scheduled for September:

  • Hickory Lane

Tree Removal in preparation for road reconstruction:

  • Hollow Swamp Road

Catch Basin Repair as scheduling allows:

  • Heritage Road (Pomperaug River Bridge to Bates Rock Road)
  • East Hill Road (Old Poverty Road to Fairway Drive)

Spot Paving this fall:

  • Cedar Trail
  • Midland Trail
  • Spring Trail

Please note: schedules subject to change due to weather conditions.